DP FMEA OMC Projects 2008-2014

OMC AB performed DP FMEA Positioning Mooring and Redundancy Test program for Det Norske Veritas DnV on behalf of Samsung Heavy Industries Co LTD & DSME Daewoo Shipbuilding and Marine Engineering in Korea 2008.

DP FMEA 2009 Singapore

Marine Operations and Support Shell Perdido Development 2009 for Shell International Exploration & Production Inc. Royal Dutch Shell's Perdido is floating in 8,000 feet of water 200 miles south of Freeport. It's a 50,000 ton structure.

2008 ,  2009, FMEA Verification Trial Program for Pipelay Barge , JASCON 25.

WEST PHOENIX    WEST HERCULES    WEST EMINENCE    JASCON 25

Shell Spar May 2009-April 2010

Shell DP & Marine Representative for SHELL SPAR  ( Moored to Ocean Floor ) PERDIDO Project, floating in 8,000 feet of water, is the world's deepest-water oil /gas drilling and production platform.

October 2010 Caesar Tonga Field GoM Suta Subsea Underwater Termination Assembly DP Project Skandi Neptune Subsea 7.

December 2010-Jan 2011 Judy Fiber Optic Pull-In PPCo DP Marine Representative onboard MPV  Volantis.

January 2011 Skandi Neptune / Subsea 7 Orskov Shipyard Denmark 10-Year Class Inspection , Installation 250T Crane.

February 2011 Project  BP E&P FPSO Schiehallion / Betty Knutsen.

March 2011 VAS Marine Inspection BP E&P Apache II.

April-May 2011 Project ConocoPhillips E&P Aberdeen Sesmic Aquisition Seismic Vessel Fairfield C-Pacer J-Block.

June 2011 VAS BP E&P Shuttle Tanker Navion Norvegia.

June 2011 BP E&P Rigmove Transocean Paul B Loyd Jr Schiehallion to Devenick 2 Field.

July 2011 - End of August 2011  BP E&P Skarv development project BP FPSO SKARV Hook-Up Installation AHTS Maersk Logger.

October 2011- End January 2012 Start BP DP Marine Representative onboard DSV Akademik Tofiq Ismayilov Azerbaijan , Caspian Sea / Deep Water Gunashli Area.

February 2012- February 2013 Start BP Marine Representative onboard Borgholm Dolphin / BP ANDREW AREA DEVELOPMENT PROJECT.

March 2013 - July 2013 BP Marine Representative onboard Safe Caledonia / BP ANDREW AREA DEVELOPMENT PROJECT.

Sept 2013 Rig Move Transocean Paul B Lloyd Jr at Clair Ridge

Nov 2013 Tow Master Heading Control Maersk FPSO North Sea Producer

Dec 2013 Rig Move Polar Pioneer Troll Area Statoil North Sea

Jan 2014 Rig Move Ocean Vanguard Askja to tastaveden Statoil Project

Feb 2014 Statoil Pre-Lay Anchor Spread at Geitungen Appraisal Statoil Project AHTS KL Sandefjord

Mar 2014 Rigmove Transocean Winner AHTS Skandi Iceman

Mar 2014 Pre-Lay anchor system for Marathon AHTS KL Saltfjord

Apr 2014 Warranty Surveyor on-board Seven Navica Oseberg Delta 2 Pipelay and Subsea Installation

 

 

 